BLOSSOM PARK
  • Home
  • Newsletters and more
    • Newsletters >
      • Sign up for our Newsletter
    • Notices >
      • Garbage
    • Annual General Meeting
  • Board of directors
  • Board members meetings
  • Contact
  • Parking
  • Policy booklet and Rules
  • Garbage
  • Drain Cleaning
  • Paving Project
  • Home
  • Newsletters and more
    • Newsletters >
      • Sign up for our Newsletter
    • Notices >
      • Garbage
    • Annual General Meeting
  • Board of directors
  • Board members meetings
  • Contact
  • Parking
  • Policy booklet and Rules
  • Garbage
  • Drain Cleaning
  • Paving Project
Search by typing & pressing enter

YOUR CART

Paving Project 

TABLE OF CONTENTS

  • PROJECT UPDATE NO. 4
  • PROJECT UPDATE NO. 3
  • IMPORTANT NOTICE TO ALL OWNERS AND RESIDENTS
  • PROJECT UPDATE NO. 2
  • PROJECT UPDATE NO. 1
  • PROJECT START NOTICE
CCC 113 - Project Update No. 4

PROJECT UPDATE NO. 4
Asphalt Reconstruction
Carleton Condominium Corporation No. 113
Ottawa, Ontario

Dear Owners and Residents,

Please find below the updated construction scheduled for the week of June 22 - 26, 2026, as provided by Thomas Cavanagh Construction Ltd. All dates are subject to weather and site conditions. In consultation with Thomas Cavanagh, we fully expect project completion by Monday, July 6th.

1. Schedule - Remainder of Project (Provided by Cavanagh, Weather Permitting)

Date Scope
Friday, June 26 Grading crew onsite - completing remedial work on standpipes
Monday, June 29 No work onsite
Tuesday, June 30 No work onsite
Wednesday, July 1 Canada Day - no work onsite
Thursday, July 2 Active Paving - driveways and top lift (wear course) placement
Friday, July 3 Line painting and grading crew onsite
Monday, July 6 Grading crew onsite - bumper curb installation

2. Parking Restrictions & Resident Responsibilities

⚠ NO PARKING ON CORPORATION PROPERTY FROM JULY 2ND to JULY 3RD, FOR ANY REASON.

⚠ PLEASE LEAVE VISITOR PARKING FOR THOSE LESS ABLE.

⚠ NO PARKING ON CARLETON CONDOMINIUM CORPORATION NO. 108 (CCC 108) AT ANY TIME.

Weather Dependent - Vehicle Access During Paving and Curing

Cavanagh has confirmed project completion on July 6, 2026, if the weather remains in our favour. We remind all Residents that parking will not be possible from Thursday July 2nd through Friday July 3rd. Please be mindful of the parking curb installation occurring on Monday, July 6th.

QUESTIONS

Please direct all questions and access requests through Sentinel Management Inc. — do not approach the contractor's crews directly on site. Contact Evan Lloyd at [email protected].

Thank you for your continued patience and cooperation as we complete this important project.

Yours Truly,
As Agents for Carleton Condominium Corporation No. 113

Noah Johnston

Chief Operating Officer
Sentinel Management Inc.

Evan M. Lloyd

Director, Strategy & Partnerships
Sentinel Management Inc.

This notice has been issued on behalf of the Board of Directors of Carleton Condominium Corporation No. 113.
For the most current project information, contact Evan Lloyd at [email protected].


CCC 113 - Project Update No. 3

PROJECT UPDATE NO. 3
Asphalt Reconstruction
Carleton Condominium Corporation No. 113
Ottawa, Ontario

Dear Owners and Residents,

Please find below the updated construction schedule for the week of June 22 - 26, 2026, as provided by Thomas Cavanagh Construction Ltd. All dates are subject to weather and site conditions. We anticipate project completion by this Friday, June 26, 2026.

1. Schedule - Remainder of Project (Provided by Cavanagh, Weather Permitting)

Date Scope
Monday, June 22 Continued paving parking stalls and driveways.
Tuesday, June 23 Top lift (wear course) paving
Wednesday, June 24 Line painting; standpipe rebuilds
Thursday, June 25 Installation of parking curbs
Friday, June 26 Landscaping adjustments

2. Parking Restrictions & Resident Responsibilities

⚠ NO PARKING ON CORPORATION PROPERTY FROM TODAY to FRIDAY, JUNE 26TH, FOR ANY REASON.
⚠ PLEASE LEAVE VISITOR PARKING FOR THOSE LESS ABLE.
⚠ NO PARKING ON CARLETON CONDOMINIUM CORPORATION NO. 108 (CCC 108) AT ANY TIME.

Weather Dependent - Vehicle Access During Paving and Curing

We are quickly approaching the end of construction activities at Carleton Condominium Corporation No. 113. We appreciate the patience shown by Owners and Residents, and kindly ask you to wait until end of day on Friday, June 26th, to return your vehicles to their parking locations. This continues to be weather dependent. Please be mindful of the parking curb installation occurring on Friday, June 26th.

Resident Services During Construction - Your Questions Answered

Para Transpo & Accessible Transport When booking, advise the operator that the property is under construction. Please arrange to meet your ride at the nearest open street entrance — typically along Queensdale Avenue. If mobility limitations make this difficult, contact Sentinel Management in advance and we will coordinate with Cavanagh to assist.
Taxi & Ride Sharing Set your pick-up/drop-off point to the street perimeter (e.g., Queensdale Avenue) rather than your unit address. Taxis and rideshare vehicles cannot enter the site during working hours (7:00 AM–5:00 PM) or during paving/curing closures.
Mail Cavanagh is coordinating directly with Canada Post and mail delivery is expected to continue. Pedestrian access to community mailboxes will be maintained throughout the work — please use caution and follow any signage or crew direction.
Deliveries (Amazon, Couriers, etc.) Couriers will not be able to drive to your door during working hours or paving closures; expect deliveries on foot or minor delays. Add delivery instructions to your orders where possible. We strongly recommend rescheduling large deliveries (furniture, appliances, moving trucks) until after June 26.
Garbage & Recycling Cavanagh is coordinating to ensure collection continues. On collection days during paving, place bins at the nearest accessible point at the edge of the work area by 7:00 AM.
Emergency Services Emergency vehicle access is being maintained at all times, in accordance with the contract requirements.

Please direct all questions and access requests through Sentinel Management Inc. — do not approach the contractor's crews directly on site. Contact Evan Lloyd at [email protected].

Thank you for your continued patience and cooperation as we complete this important project.

Yours Truly,
As Agents for Carleton Condominium Corporation No. 113

Noah Johnston

Chief Operating Officer
Sentinel Management Inc.

Evan M. Lloyd

Director, Strategy & Partnerships
Sentinel Management Inc.

This notice has been issued on behalf of the Board of Directors of Carleton Condominium Corporation No. 113.
For the most current project information, contact Evan Lloyd at [email protected].


CCC 113 - Reminder Notice for Owners and Residents
IMPORTANT NOTICE TO ALL OWNERS AND RESIDENTS

Asphalt Reconstruction
Carleton Condominium Corporation No. 113
Ottawa, Ontario

Dear Owners and Residents,

The Board of Directors and Sentinel Management wish to remind all owners, residents, and their guests that this community is shared by 135 households. The stress of an active construction project does not diminish the obligation of every member of this community to treat one another - and Corporation staff, Board members, and contractor personnel - with courtesy and respect.

CCC No. 113 maintains a zero-tolerance policy with respect to harassment. This applies equally to:

  • Aggressive, threatening, or intimidating behaviour toward neighbours, Board Members, or Sentinel staff;
  • Rude, demeaning, or verbally abusive conduct, whether in person, by telephone, or in writing;
  • And any conduct that constitutes harassment as defined under the Ontario Health and Safety Act, or applicable legislation.

Residents who experience or witness such conduct are encouraged to report it in writing to Sentinel Management at the contact information below. The Corporation reserves the right to pursue all available legal remedies in response to confirmed incidents of harassment, including recovery of associated costs from the responsible unit owner.

1. VEHICLE & PARKING RESTRICTIONS - JUNE 16 TO JUNE 22, 2026

Pavement reconstruction has now entered the asphalt paving phase. The base lift of asphalt is currently being completed on the roadways, with the top lift of asphalt scheduled for June 18th and 19th. During this critical paving window, vehicular traffic on Corporation roadways, parking areas, and driveways will cause permanent damage to the fresh asphalt surface.

Effective immediately and through June 22, 2026:

  • NO personal vehicles are permitted to drive on or park on Corporation property.
  • This restriction applies 24 hours per day, 7 days per week, for the duration of this notice period (June 16 - June 22, 2026).

TOWING ENFORCEMENT

Any vehicle found on Corporation Property will be towed at the Owner's expense, without further warning. Vehicles will be relocated to any available space on Queensdale Avenue, or, if no legal spaces remain, to any available space. The Corporation assumes no liability for vehicles towed during this period.

QUESTIONS

We recognize that this restriction is an inconvenience and sincerely appreciate your patience and cooperation as we complete this significant investment in the property. We anticipate normal vehicle access will resume following the completion of the paving, weather dependent, on June 22, 2026.

Please direct all questions and access requests through Sentinel Management Inc. - do not approach the contractor's crews directly on site. Contact Evan Lloyd at [email protected].

Thank you for your continued patience and cooperation as we complete this important project.

Yours Truly,
As Agent for Carleton Condominium Corporation No. 113

Even M. Claugh

Noah Johnston

Chief Operating Officer
Sentinel Management Inc.

Evan Lloyd

Director, Strategy & Partnerships
Sentinel Management Inc.

This notice has been issued on behalf of the Board of Directors of Carleton Condominium Corporation No. 113.
For the most current project information, contact Evan Lloyd at [email protected].


CCC 113 – Project Update No. 2

PROJECT UPDATE NO. 2

Asphalt Reconstruction
Carleton Condominium Corporation No. 113
Ottawa, Ontario

Dear Owners and Residents,

Work is progressing well and on schedule. Grading of the granular base is nearly complete, the soft area at the common walkway between 3179/3181 Stockton has been repaired, and the consulting engineer (Paterson Group Inc.) has confirmed that all work to date is in general conformance with the project documents. This update provides the confirmed schedule for the remainder of the project and answers the questions we have received from residents about day-to-day services during paving.

1. Schedule – Remainder of Project
DateScope
Friday, June 12Pour concrete, Pave base lift asphalt
Monday, June 15No work on site
Tuesday, June 16Finish Base lift, Start Driveway Paving
Wednesday, June 17Iron adjustments (maintenance hole covers, frames, valves)
Thursday, June 18Top lift (final surface) asphalt paving
Friday, June 19Continue top lift paving; line painting
Mon–Tues, June 22–23Precast curbs and bumper curbs
Wednesday, June 24Landscaping adjustments
2. Parking Restrictions & Resident Responsibilities

⚠ NO PARKING ON CORPORATION PROPERTY FROM FRIDAY, JUNE 12 – SUNDAY, JUNE 21 FOR ANY REASON.

⚠ PLEASE LEAVE VISITOR PARKING FOR THOSE LESS ABLE.

⚠ NO PARKING ON CCC 108 AT ANY TIME.

⚠ BE AWARE OF UNRELATED WORK ALONG QUEENSDALE.

Vehicle Access During Paving and Curing – Important

To date, Cavanagh has been very accommodating to residents who require vehicle access to the site, and we thank them for that flexibility. However, with asphalt placement beginning next week, this will change:

  • Effective Friday, June 12: No parking anywhere on Corporation Property until paving is complete and asphalt has cured. All vehicles must be removed before 7:30 AM.
  • No exceptions will be made. Vehicles left on the property will be towed to available space along Queensdale Avenue at the owner’s risk.
Resident Services During Construction – Your Questions Answered
Para Transpo & Accessible Transport Advise operators the property is under construction. On paving days (June 12–19), meet rides at the nearest open street entrance (typically Queensdale Avenue). Contact Sentinel if mobility limitations require assistance.
Taxi & Ride Sharing Set pickup/dropoff to the street perimeter. Vehicles cannot enter the site during working hours or paving closures.
Mail Mail delivery will continue. Pedestrian access to mailboxes will be maintained.
Deliveries Couriers cannot drive to your door during working hours. Expect on‑foot delivery or delays. Reschedule large deliveries until after June 25.
Garbage & Recycling Collection will continue. Place bins at the nearest accessible point by 7:00 AM.
Emergency Services Emergency access is maintained at all times.
Parking Permits – Status Update

No new developments at this time. Resident parking remains unavailable until the asphalt has cured and the property reopens on Monday, June 22.

Questions

Please direct all questions and access requests through Sentinel Management Inc. Contact Evan Lloyd at [email protected].

Yours Truly,
As Agent for Carleton Condominium Corporation No. 113

Noah Johnston
Chief Operating Officer
Sentinel Management Inc.

Evan Lloyd
Director, Strategy & Partnerships
Sentinel Management Inc.

This notice has been issued on behalf of the Board of Directors of Carleton Condominium Corporation No. 113.


CCC 113 – Project Update No. 1

PROJECT UPDATE NO. 1

Asphalt Reconstruction
Carleton Condominium Corporation No. 113
Ottawa, Ontario

Dear Owners and Residents,

Construction of the Asphalt Reconstruction Project commenced June 1, 2026, and is progressing ahead of schedule. This update provides the current project status based on the consultant's field reporting through the work undertaken this week, the upcoming week's schedule from Cavanagh, and important reminders regarding parking and resident responsibilities.

1. Project Status – as of June 3, 2026

Approximately 90% of pavement demolition, excavation, and removals are complete across the property. Remaining sections include the property entrances, and the common walkway between 3179/3181 Stockton. Contractors have completed saw-cutting of all disturbed pavement edges. Roadway grade surveying is well underway.

The Schedule for work is progressing ahead of schedule. Grading is set to be completed by June 10; base lift of paving will begin on June 11th, with paving activities expected to conclude by end of day on June 19th, 2026. We remind all parties that the schedule provided by Thomas Cavanagh Construction Ltd. is subject to change due to weather or site conditions. Further updates will be communicated as work progresses.

2. Parking Restrictions & Resident Responsibilities

A NO PARKING ON CORPORATION PROPERTY – EXCEPT FOR FRIDAY 6:00 PM TO SUNDAY 8:00 PM
A NO PARKING ON CARLETON CONDOMINIUM CORPORATION NO. 108 (CCC 108) AT ANY TIME

All vehicles must be removed from Corporation property before 6:30 AM on each working day. Vehicles remaining onsite after 6:30 AM will be towed at the owner's expense. Contractors will tow vehicles to any available side street if left on the property, without notice. Residents leave vehicles at their own risk.

3. Engagement with City of Ottawa

As communicated in the Project Start Notice, it is the Resident's responsibility to make alternate parking arrangements for the duration of active paving work at the Corporation. Management has been in daily conversation with the Board of Directors and the City of Ottawa to assist Residents with the parking displacement through this project. We will send further communications on these endeavors as information is returned to our office by the City.

4. Project Team & Contact Information

Should you have any questions or concerns regarding the project, please contact the Project Coordination Office and/or your Condominium Manager. Do not approach the contractor's crews directly on-site; all inquiries should be directed through Sentinel Management Inc.

Role Organization Contact
Condominium Management Sentinel Management Inc. Evan Lloyd – [email protected]
Condominium Manager Sentinel Management Inc. Noah Johnston – [email protected]
Contractor Thomas Cavanagh Construction Ltd. Contact via management
Consulting Engineer Paterson Group Inc. Contact via management

We appreciate your patience and cooperation throughout this important project. The pavement reconstruction work is essential to preserving the long-term integrity of the common elements and ensuring the continued safety of all roadways, parking areas, and driveways throughout the complex. Regular updates will be provided as the project progresses.

Yours Truly,
As Agents for Carleton Condominium Corporation No. 113

Noah Johnston
Chief Operating Officer

Evan Lloyd
Director, Strategy & Partnerships


CCC 113 - Project Start Notice

PROJECT START NOTICE

Asphalt Pavement Rehabilitation

Carleton Condominium Corporation No. 113

Ottawa, Ontario


Dear Owners and Residents,

On behalf of the Board of Directors of Carleton Condominium Corporation No. 113 (CCC 113) and Sentinel Management Inc., we are pleased to advise that the Asphalt Replacement Project will commence Monday, June 1, 2026.

1. Project Overview

Following engineering review by Paterson Group Inc., Thomas Cavanagh Construction Ltd. has been selected to complete the project.

PropertyQueensdale Avenue, Stockton Drive, Hogarth Avenue and Fenmore Street
CorporationCCC 113
Property ManagementSentinel Management Inc.
ContractorThomas Cavanagh Construction Ltd.
Consulting EngineerPaterson Group Inc.
Work Start DateJune 1, 2026
Estimated CompletionEnd of June 2026
Daily Work HoursMonday – Friday, 07:00 – 17:00

2. Construction Schedule

ActivityStartDurationFinish
Mobilization & Site PrepJune 13 daysJune 3
Asphalt RemovalJune 25 daysJune 8
Concrete WorksJune 111 dayJune 11
Grading WorksJune 56 daysJune 12
Fine GradingJune 151 dayJune 15
Base UpgradesJune 112 daysJune 12
Base AsphaltJune 161 dayJune 16
Iron AdjustmentsJune 182 daysJune 19
Top AsphaltJune 222 daysJune 23
Final WorksJune 234 daysJune 26
CompletionJune 301 dayJune 30

Schedule is weather permitting and may change.

3. Resident Responsibilities

Before Work Begins

  • Remove all vehicles from work zones
  • Arrange alternate parking
  • Remove items near driveways
  • Clear landscaping within 1 foot

Vehicle Removal

All vehicles must be removed by 6:30 AM daily.

Vehicles left in work zones will be towed at owner's expense.

Access Restrictions

NO VEHICLE OR PEDESTRIAN ACCESS IN ACTIVE WORK ZONES

Safety

  • Follow all signage
  • Use caution near construction
  • Keep children away

4. Scope of Work

  • Removal of asphalt
  • Base reconstruction
  • Grading and drainage
  • Curb repairs
  • New asphalt installation
  • Landscaping restoration

5. Site Logistics

  • Work hours: 07:00–17:00
  • Parking closures
  • Traffic control in effect
  • Noise and dust expected

6. Contact Information

RoleOrganizationContact
Management Sentinel Management Inc. Evan Lloyd – [email protected]
Noah Johnston – [email protected]
Contractor Thomas Cavanagh Construction Ltd. Contact via management
Engineer Paterson Group Inc. Contact via management

We appreciate your patience and cooperation.